All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Inspect, record and report condition of Medium/High Voltage station apparatus and related equipment |
SAQA US ID | UNIT STANDARD TITLE | |||
259207 | Inspect, record and report condition of Medium/High Voltage station apparatus and related equipment | |||
ORIGINATOR | ||||
SGB Electrical Engineering & Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Electrical Infrastructure Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 4 | NQF Level 04 | 6 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard replaces: |
US ID | Unit Standard Title | Pre-2009 NQF Level | NQF Level | Credits | Replacement Status |
113969 | Inspect, record and report condition of Medium / High Voltage station apparatus and related equipment | Level 4 | NQF Level 04 | 6 |
PURPOSE OF THE UNIT STANDARD |
This unit standard is for persons in the electrical Medium/High Voltage reticulation/distribution environment.
A person credited with this unit standard will be able to do the following on Medium/High Voltage station apparatus: This unit standard will contribute to the full development of the learner within the electrical engineering and construction environment by providing recognition, further mobility and transportability within the field of Physical Planning and Construction. The skills, knowledge and understanding demonstrated within this unit standard are essential for social and economic transformation and upliftment within the electrical engineering and construction environment. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
The following knowledge, skills attitude and/or equivalent:
|
UNIT STANDARD RANGE |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Plan and prepare to inspect Medium/High Voltage station apparatus and related equipment. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Job instructions are obtained and the station/apparatus/related equipment to be inspected is identified according to geographical/electrical network diagrams. |
ASSESSMENT CRITERION 2 |
Task instructions are interpreted and a sequence of operation is planned. |
ASSESSMENT CRITERION 3 |
Access to the affected station/apparatus/related equipment is arranged according to job instructions or breakdown reports where necessary. |
ASSESSMENT CRITERION 4 |
Appropriate inspection sheets/data recording equipment are identified and obtained according to data management requirements. |
SPECIFIC OUTCOME 2 |
Inspect and identify defects on Medium/High Voltage station apparatus and associated hardware. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Conditions are assessed and safety measures implemented according to safe work procedures. |
ASSESSMENT CRITERION 2 |
The condition of station apparatus/hardware is visually inspected from ground level according to routine/breakdown inspection procedures. |
ASSESSMENT CRITERION 3 |
The condition of station apparatus/hardware is recorded according to inspection sheet/data recording requirements. |
ASSESSMENT CRITERION 4 |
Safety precautions/procedures are followed before, during and after inspection. |
SPECIFIC OUTCOME 3 |
Inspect, record readings and carry out functional tests on Medium/High Voltage station. |
OUTCOME NOTES |
Inspect, record readings and carry out functional tests on Medium/High Voltage station related equipment. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Conditions are assessed and safety measures implemented according to safe work procedures. |
ASSESSMENT CRITERION 2 |
The station related equipment is visually inspected according to routine/breakdown inspection procedures. |
ASSESSMENT CRITERION 3 |
Readings are recorded and abnormalities are noted for follow-up according to inspection sheet/data recording requirements. |
ASSESSMENT CRITERION 4 |
Alarms, indications and auxiliaries are manually tested for functionality and malfunctioning/abnormalities noted for follow-up according to inspection sheet/ data recording requirements. |
SPECIFIC OUTCOME 4 |
Complete the work task. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Manually tested station related equipment is restored to operational state according to applicable standards/local requirements. |
ASSESSMENT CRITERION 2 |
Access to station and related equipment is restored/restricted as per locking system policy. |
ASSESSMENT CRITERION 3 |
Inspection sheets/recorded data is submitted/processed according to local data management systems/procedures. |
ASSESSMENT CRITERION 4 |
Serious defects/hazards are reported for immediate follow-up/rectification as per local fault reporting procedures. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Knowledge that will help me understand and that I will be able to explain:
|
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identifying and solving problems in which responsible decisions have been made regarding the inspection/defect identification of electrical station hardware/equipment. |
UNIT STANDARD CCFO WORKING |
Working effectively with others as a member of the electrical maintenance team. |
UNIT STANDARD CCFO ORGANISING |
Organising and managing oneself and one`s activities, responsibly and effectively. |
UNIT STANDARD CCFO COLLECTING |
Collecting, analysing, organising and critically evaluating information. |
UNIT STANDARD CCFO COMMUNICATING |
Communicating effectively, using visual and/or language skills by means of oral/written reports. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
This unit standard replaces unit standard 113969, " Inspect, record and report condition of Medium/High Voltage station apparatus and related equipment", Level 4, 6 credits. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Elective | 72052 | Further Education and Training Certificate: Electrical Engineering | Level 4 | NQF Level 04 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | As per Learning Programmes recorded against this Qual |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | ESKOM GENERATION - PALMIET PUMP STORAGE GRABOUW |
2. | KP ACADEMY (PTY) LTD |
3. | POWER SYSTEMS TRAINING, CAPE TOWN |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |