All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Determine the work required to accomplish the objectives and organise the scope of a simple to moderately complex project |
SAQA US ID | UNIT STANDARD TITLE | |||
243811 | Determine the work required to accomplish the objectives and organise the scope of a simple to moderately complex project | |||
ORIGINATOR | ||||
SGB Project Management | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 03 - Business, Commerce and Management Studies | Project Management | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular-Fundamental | Level 5 | Level TBA: Pre-2009 was L5 | 7 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
Learners credited with this unit standard will be able to determine the work required to accomplish the objectives of a simple to moderately complex project. Learners will be able to compile a project scope statement that provides for project requirements, assumptions and constraints. Learners will also be able to determine an appropriate approach to ensure that the work of the project is decomposed to an appropriate level of detail. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
It is assumed that learners are competent in:
|
UNIT STANDARD RANGE |
Simple to moderately complex project can be defined as projects that have:
|
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Refine the project scope statement. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The preliminary scope statement as well as other relevant inputs are reviewed and understood in order to develop a more detailed project scope statement. |
ASSESSMENT CRITERION RANGE |
Relevant inputs include but are not limited to the project brief, project charter, stakeholder expectations and requirements of the project. |
ASSESSMENT CRITERION 2 |
Project requirements, assumptions and constraints are refined using project management principles to meet project objectives. |
ASSESSMENT CRITERION 3 |
The project scope statement is compiled so that it provides for the project requirements, assumptions and constraints. |
ASSESSMENT CRITERION 4 |
The project scope statement is documented in the required format and agreed with relevant stakeholders in required timeframe. |
SPECIFIC OUTCOME 2 |
Determine the approach for decomposing the work of the project. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Components into which work needs to be decomposed (horizontal division) are determined using project management principles to support the planning and control of the project. |
ASSESSMENT CRITERION RANGE |
Components include but are not limited to project phases, disciplines, geographic areas and products. |
ASSESSMENT CRITERION 2 |
The level of detail to which work is decomposed (vertical division) is determined using project management principles in order to support the planning and control of the project. |
SPECIFIC OUTCOME 3 |
Decompose the work of the project into components to the required level of detail. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The work of the project is decomposed into major deliverables or subprojects to support the planning and control of the project. |
ASSESSMENT CRITERION RANGE |
Work may be broken down to multiple levels depending on aspects such as management control and risks. |
ASSESSMENT CRITERION 2 |
Each component of work is coded in accordance with required organisational procedures to enable unique identification. |
ASSESSMENT CRITERION 3 |
Completion criteria is determined for each component to support the planning and control of the project. |
ASSESSMENT CRITERION 4 |
The decomposed work is documented in the Work Breakdown Structure (WBS) format required by the organisation. |
ASSESSMENT CRITERION 5 |
Details of the components are documented in the Work Breakdown Structure dictionary to explain and communicate the requirements and completion criteria. |
ASSESSMENT CRITERION 6 |
The Work Breakdown Structure is verified and approved in the required format by relevant stakeholders. |
ASSESSMENT CRITERION 7 |
Roles and responsibilities for work components are defined in required format and in accordance with project requirements. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO WORKING |
Work effectively with others when determining the approach for decomposing the work of a project to support the panning and control of the project. |
UNIT STANDARD CCFO ORGANISING |
Organise and manage oneself and one's activities when decomposing components of work. |
UNIT STANDARD CCFO COLLECTING |
Collect, evaluate, organise and critically evaluate information when reviewing the preliminary scope statement and other relevant inputs. |
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively when including components and completion criteria into the Work Breakdown Structure dictionary. |
UNIT STANDARD CCFO SCIENCE |
Use science and technology when documenting the decomposed work in the Work Breakdown Structure format. |
UNIT STANDARD CCFO DEMONSTRATING |
Demonstrate an understanding of the world as a set of related systems whereby understanding that unless the work is included in the Work Breakdown Structure it is not considered part of the project scope, therefore will not be done. |
UNIT STANDARD CCFO CONTRIBUTING |
In order to contribute to the full personal development of each learner and the social and economic development of society at large, it must be the intention underlying any programme of learning to make an individual aware of the importance of reflecting on and exploring a variety of strategies to learn more effectively. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
Terms, techniques and processes referred to in this unit standard are based upon recognised best practice for generic project management reflected in industry standards such as:
> A Guide to the Project Management Body of Knowledge (PMBoK Guide), 2000 and 2004 versions, from Project Management Institute (PMI®). > Extensions to PMBoK® Guide from PMI®. > Work Breakdown Structure. > Earned Value. |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 58395 | National Certificate: Project Management | Level 5 | Level TBA: Pre-2009 was L5 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | SERVICES |
Core | 58309 | National Diploma: Project Management | Level 5 | NQF Level 05 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | SERVICES |
Elective | 65649 | National Certificate: Official Statistics | Level 5 | Level TBA: Pre-2009 was L5 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | PSETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |