All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Prepare a site for ceiling and partition installation |
SAQA US ID | UNIT STANDARD TITLE | |||
243757 | Prepare a site for ceiling and partition installation | |||
ORIGINATOR | ||||
SGB Building Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Building Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 3 | NQF Level 03 | 13 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2026-06-30 | 2029-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
Qualifying learners are capable of:
> Partition framework. > Residential, dry wall and de-mountable partitioning framework. > Window and door frames. These skills will contribute towards the overall efficiency of their employer organisations and ensure that breakages and work stoppages are kept to a minimum and that equipment is used in accordance with best practice and safety procedures. This competence also advances a learner's personal expertise and employability in the construction sector and related fields, for example, interior design and refurbishment. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
It is assumed that learners already competent in the following:
|
UNIT STANDARD RANGE |
Preparation includes but not limited to a site for:
|
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Prepare for framework construction. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Floor protection is installed in accordance with construction procedures. |
ASSESSMENT CRITERION 2 |
Materials and tools are laid out in a logical fashion. |
ASSESSMENT CRITERION 3 |
Frame locations are accurately measured and correctly marked out. |
ASSESSMENT CRITERION 4 |
Scaffolding and support mechanisms are prepared safely. |
SPECIFIC OUTCOME 2 |
Construct a suspended ceiling framework. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The installation of a screw-up suspended ceiling is demonstrated. |
ASSESSMENT CRITERION 2 |
The installation of a sub grid suspended ceiling is demonstrated. |
ASSESSMENT CRITERION 3 |
The installation of an Exposed Tee suspended ceiling is demonstrated. |
ASSESSMENT CRITERION 4 |
The installation of insulation and acoustic/isolation material is demonstrated. |
ASSESSMENT CRITERION 5 |
Prescribed safety procedures are adhered to. |
ASSESSMENT CRITERION 6 |
Housekeeping guidelines as defined by the workplace standards and norms are adhered to. |
SPECIFIC OUTCOME 3 |
Construct a framework for residential partitioning. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Material is accurately measured and cut correctly. |
ASSESSMENT CRITERION RANGE |
The range includes the use of straight sections, ends, corners and studs used in basic partitions and the construction of special partitions such as niche walls and extra high walls. |
ASSESSMENT CRITERION 2 |
The frame is fixed to supporting structures correctly. |
ASSESSMENT CRITERION 3 |
The installation of Nogging is demonstrated following installation procedures. |
ASSESSMENT CRITERION NOTES |
Nogging is the installation of horizontal support for heavy objects including but not limited to shelves and basins. |
ASSESSMENT CRITERION 4 |
The installation of Bracing is demonstrated. |
ASSESSMENT CRITERION NOTES |
Bracing is the installation of horizontal support for openings including but not limited to serving hatches and large windows. |
ASSESSMENT CRITERION 5 |
The application of insulation and acoustic material to the framework is demonstrated. |
ASSESSMENT CRITERION 6 |
Prescribed safety procedures are adhered to. |
ASSESSMENT CRITERION 7 |
Housekeeping guidelines as defined by the workplace standards and norms are adhered to. |
SPECIFIC OUTCOME 4 |
Construct a dry wall framework. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Material is measured and cut accurately. |
ASSESSMENT CRITERION RANGE |
The range includes the use of straight sections, ends, corners and studs used in basic partitions and the construction of special partitions such as curved walls, extra high walls and cinema walls. |
ASSESSMENT CRITERION 2 |
The frame is fixed to supporting structures. |
ASSESSMENT CRITERION 3 |
The application of insulation and acoustic material to partitioning is demonstrated. |
ASSESSMENT CRITERION 4 |
Prescribed safety procedures are adhered to. |
ASSESSMENT CRITERION 5 |
Housekeeping guidelines standards and norms are adhered to as defined by the workplace. |
SPECIFIC OUTCOME 5 |
Construct a de-mountable framework. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Material is measured and cut correctly. |
ASSESSMENT CRITERION RANGE |
The range includes the use of straight sections, ends, corners and studs used in basic partitions and the construction of special partitions such as curved walls, extra high walls and cinema walls. |
ASSESSMENT CRITERION 2 |
The frame is fixed to supporting structures. |
ASSESSMENT CRITERION 3 |
The application of insulation and acoustic material to the framework is demonstrated correctly. |
ASSESSMENT CRITERION 4 |
Prescribed safety procedures are adhered to. |
ASSESSMENT CRITERION 5 |
Housekeeping guidelines standards and norms are adhered to as defined by the workplace. |
SPECIFIC OUTCOME 6 |
Construct door and window frames. |
OUTCOME RANGE |
The range of frames includes aluminium-; wood- and steel frames. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Door and window frameworks are installed with adequate support. |
ASSESSMENT CRITERION 2 |
Door and window frameworks are constructed on square and correctly sized. |
ASSESSMENT CRITERION 3 |
Door/window frames are correctly installed. |
SPECIFIC OUTCOME 7 |
Construct a direct-fix ceiling framework. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
The installation of a nail up (wood branding) direct fix ceiling is demonstrated. |
ASSESSMENT CRITERION 2 |
The installation of steel branding direct fix ceiling is demonstrated. |
ASSESSMENT CRITERION 3 |
The installation of insulation and acoustic/isolation material is demonstrated. |
ASSESSMENT CRITERION 4 |
Prescribed safety procedures are adhered to. |
ASSESSMENT CRITERION 5 |
Housekeeping guidelines as defined by the workplace standards and norms are adhered to. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
Qualifying learners understand and are competent to explain how to:
> Framework for residential partitioning. > Dry wall framework. > De-mountable framework. > Door and window frames. > Prescribed safety procedures. > Best practice housekeeping standards and norms. |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems by taking responsible decisions, thereby demonstrating critical evaluation and creative thinking in applying knowledge of a range of partitioning and components, selecting appropriate products for use in specified situations and ensuring adherence to best practice industry/housekeeping standards and norms. |
UNIT STANDARD CCFO WORKING |
Work effectively as a member of a team for example, by physically handling/constructing/fixing/installing a range of partitioning and components with the assistance of other team members. |
UNIT STANDARD CCFO ORGANISING |
Organise and manage themselves and their own activities responsibly and effectively when preparing for the construction of a range of partitioning frameworks by working in an organised manner. |
UNIT STANDARD CCFO COLLECTING |
Collect, analyse, organise and critically evaluate information by adhering to prescribed best practice housekeeping standards and norms on the installation site and selecting the correct tools and materials for the project. |
UNIT STANDARD CCFO SCIENCE |
Apply mathematical principles when measuring frame locations and taking measurements of material before cutting. |
UNIT STANDARD CCFO DEMONSTRATING |
Demonstrate awareness that problem-solving contexts do not exist in isolation by recognising and understanding that the:
|
UNIT STANDARD CCFO CONTRIBUTING |
Contribute to their own full development and the social and economic development of society at large. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
N/A |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 58247 | National Certificate: Ceiling and Partitioning Installation | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
Elective | 65409 | National Certificate: Building and Civil Construction | Level 3 | NQF Level 03 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | Akaf Bodyguards |
2. | Aveng Grinaker -LTA Civil Engineering |
3. | Better Best Agri Development |
4. | Bhekwell Group |
5. | BOLAND COLLEGE (Paarl) |
6. | Certified Training Solutions (Pty) Ltd |
7. | Ekurhuleni Artisans and Skills Training Pty Ltd |
8. | Elangeni College for FET - Central Office |
9. | Goitsebasadi Construction Project |
10. | Goldfields FET College |
11. | Leps Training Consultants |
12. | LNT Trading Enterprise |
13. | Mahumani Empowerment Servives Centre |
14. | Majuba TVET College |
15. | Mavco Engineering |
16. | Mnambithi TVET College |
17. | MOLOKO SMALL ENTERPRISE |
18. | MPUMALANGA REGIONAL TRAINING TRUST |
19. | Novi General Services |
20. | PIONEER BUSINESS CONSULTING (PTY) LTD |
21. | Primeserv Corporate Solutions (Pty) Ltd |
22. | Raubex Construction Pty (Ltd) |
23. | RESISA LOGISTICS (Ltd) Pty |
24. | Sakhisizwe Development Training |
25. | Sheq and Environmental Projects |
26. | Sonani Training and Communications |
27. | Tjeka Training Matters Pty Ltd |
28. | Tovani Traiding 299 |
29. | Tshwane North College for FET - Central Office |
30. | Umfolozi FET College |
31. | West Coast TVET College |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |