All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Maintain the quality of power supply in terms of frequency on electrical transmission systems |
SAQA US ID | UNIT STANDARD TITLE | |||
242776 | Maintain the quality of power supply in terms of frequency on electrical transmission systems | |||
ORIGINATOR | ||||
SGB Power Plant Operations | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 06 - Manufacturing, Engineering and Technology | Engineering and Related Design | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 5 | Level TBA: Pre-2009 was L5 | 18 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2024-06-30 | 2027-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
Persons credited with this unit standard is able to Operate Automatic Generator Control (AGC), implement tie-line contracts, follow load according to Area Control Error (ACE), time error under normal and abnormal system conditions. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
Learning Assumed to have taken place:
|
UNIT STANDARD RANGE |
National and International electrical transmission systems. |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Implement SAPP tie-line hourly contracts. |
OUTCOME RANGE |
Contracted and revisions. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Relevant energy contracts are sourced according to requirements. |
ASSESSMENT CRITERION 2 |
Information is captured accurately and recorded according to organisational requirements. |
ASSESSMENT CRITERION 3 |
Information processed is verified according to requirements. |
ASSESSMENT CRITERION 4 |
Energy contracts are implemented according to requirements. |
SPECIFIC OUTCOME 2 |
Perform loading according to Area Control Error (ACE). |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Tie line Bias Control mode is selected according to Southern African Power Pool criteria, Eskom Power Pool Rules and ancillary agreements/contracts. |
ASSESSMENT CRITERION 2 |
Area Control Error is controlled within parameters according to Southern African Power Pool agreements, Eskom Power Pool Rules and Ancillary agreements/contracts. |
ASSESSMENT CRITERION 3 |
Load following is performed according to statutory requirements, system operating guidelines, procedures and Southern African Power Pool agreements, Eskom Power Pool Rules and ancillary agreements/contracts. |
ASSESSMENT CRITERION 4 |
Adjustments are performed according to load following Schedule Program, reserve market merit order, regulations and procedures. |
ASSESSMENT CRITERION RANGE |
Automatic Generator Control modes, up and down regulation, generator upper and lower limits. |
ASSESSMENT CRITERION 5 |
Time error is controlled within parameters and as per SAPP agreements. |
ASSESSMENT CRITERION 6 |
Synchronized reserves are monitored in accordance to operating procedures/requirements. |
ASSESSMENT CRITERION 7 |
Instructions are issued in accordance to regulatory requirements. |
SPECIFIC OUTCOME 3 |
Monitor tie-line power flow. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
SAPP Energy contracts are correctly captured in Electronic Information System. |
ASSESSMENT CRITERION 2 |
Information is continuously monitored to ensure generation capacity meets the actual demand. |
ASSESSMENT CRITERION 3 |
Specific response procedures are applied in accordance with operating requirements when alarms are set. |
ASSESSMENT CRITERION 4 |
Information is obtained, updated, logged and communicated to the relevant key receivers according to standards and operating guidelines. |
ASSESSMENT CRITERION 5 |
Information obtained is interpreted and verified against contract and actual demand or trends. |
SPECIFIC OUTCOME 4 |
Control abnormal system conditions. |
OUTCOME RANGE |
Automatic Generator Control mode changes, loss of tie-line or declared emergencies, Southern African Power Pool surpluses and shortages. Eskom Power Pool Rules and Ancillary agreements/contracts, tie-line load fluctuations, data failure. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
Abnormal conditions are identified according to requirements. |
ASSESSMENT CRITERION 2 |
Abnormal conditions are analysed by comparing actual conditions with required conditions. |
ASSESSMENT CRITERION 3 |
Possible solutions are determined to ensure minimum risk to system. |
ASSESSMENT CRITERION 4 |
Corrective action is implemented as per system operating guidelines, procedures and agreements. |
ASSESSMENT CRITERION 5 |
Actions implemented are reviewed as per operating guidelines, policies. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identifying and solving problems in which responses display that responsible decisions using critical and creative thinking have been made. |
UNIT STANDARD CCFO WORKING |
Working effectively with others as a member of a team, group, organization, and community. |
UNIT STANDARD CCFO ORGANISING |
Organising and managing oneself and one's activities responsibly and effectively. |
UNIT STANDARD CCFO COLLECTING |
Collecting, analysing, organizing and critically evaluating information. |
UNIT STANDARD CCFO COMMUNICATING |
Communicating effectively using visual, mathematical and/or language skills in the modes of oral and/or written persuasion. |
UNIT STANDARD CCFO SCIENCE |
Using science and technology effectively and critically, showing responsibility towards the environment and health of others. |
UNIT STANDARD CCFO DEMONSTRATING |
Demonstrating an understanding of the world as a set of related systems by recognizing that problem-solving contexts do not exist in isolation. |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
N/A |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 57693 | National Diploma: Electrical Network Power Dispatch Controlling | Level 5 | NQF Level 05 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | EWSETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
NONE |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |