All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |
SOUTH AFRICAN QUALIFICATIONS AUTHORITY |
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: |
Survey and set out construction work areas |
SAQA US ID | UNIT STANDARD TITLE | |||
15149 | Survey and set out construction work areas | |||
ORIGINATOR | ||||
SGB Building Construction | ||||
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY | ||||
- | ||||
FIELD | SUBFIELD | |||
Field 12 - Physical Planning and Construction | Building Construction | |||
ABET BAND | UNIT STANDARD TYPE | PRE-2009 NQF LEVEL | NQF LEVEL | CREDITS |
Undefined | Regular | Level 5 | Level TBA: Pre-2009 was L5 | 15 |
REGISTRATION STATUS | REGISTRATION START DATE | REGISTRATION END DATE | SAQA DECISION NUMBER | |
Passed the End Date - Status was "Reregistered" |
2018-07-01 | 2023-06-30 | SAQA 06120/18 | |
LAST DATE FOR ENROLMENT | LAST DATE FOR ACHIEVEMENT | |||
2026-06-30 | 2029-06-30 |
In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise. |
This unit standard does not replace any other unit standard and is not replaced by any other unit standard. |
PURPOSE OF THE UNIT STANDARD |
Learners who are assessed as competent against this unit standard will be able to understand and apply surveying techniques and principles, including tachometric principlesThis competence complements the other management competencies and underpins the Elective learning. It contributes to the development of a professional community of Building Construction Managers. The contribution to The National Skills Development Strategy is the key developmental interface between learners and new competencies to be achieved. Its contribution to socio-economic transformation is that learners would be able to undergo RPL-assessment and thereby receive recognition for previous learning and experience. The employability and career prospects of learners can therefore be enhanced by this qualification. |
LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING |
FETC |
UNIT STANDARD RANGE |
Specific Outcomes and Assessment Criteria: |
SPECIFIC OUTCOME 1 |
Understand and apply surveying techniques and principles. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Setting out principles are explained |
ASSESSMENT CRITERION 2 |
2. Reference and survey control systems are established |
ASSESSMENT CRITERION 3 |
3. The techniques for setting out positions, levels (elevations) and slopes from established points are applied |
ASSESSMENT CRITERION 4 |
4. Information regarding dimensions and positions for surveying is extracted from drawings |
ASSESSMENT CRITERION 5 |
5. Survey errors are identified and eliminated in accordance with surveying principles |
SPECIFIC OUTCOME 2 |
Set out and check levels and profiles. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Levels are set out and transferred in accordance with survey information and drawings |
ASSESSMENT CRITERION 2 |
2. Profiles are established for construction works in accordance with drawings |
ASSESSMENT CRITERION 3 |
3. All surveying and setting out activities are checked to comply with survey information and drawings |
SPECIFIC OUTCOME 3 |
Apply tachometric principles and set out construction works. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. The principles of tachometry are applied in setting out and collection of data |
ASSESSMENT CRITERION 2 |
2. All surveying and setting out activities are checked to comply with survey information and drawings |
ASSESSMENT CRITERION 3 |
3. Tache principles are applied to produce a tache survey and contour plan |
SPECIFIC OUTCOME 4 |
Collect site data and prepare as-built drawings. |
ASSESSMENT CRITERIA |
ASSESSMENT CRITERION 1 |
1. Information on site regarding existing services, features and structures, is collected using measurement and surveying techniques |
ASSESSMENT CRITERION 2 |
2. Changes made to design that are incorporated in the permanent works are recorded according to site record keeping principles |
ASSESSMENT CRITERION 3 |
3. Deviations from original project information that may affect future works or maintenance are recorded according to site record keeping principles |
ASSESSMENT CRITERION 4 |
4. Information gathered is assimilated and incorporated in as-built drawings according to industry accepted drawings standards, and client requirements. |
UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS |
UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE |
UNIT STANDARD DEVELOPMENTAL OUTCOME |
N/A |
UNIT STANDARD LINKAGES |
N/A |
Critical Cross-field Outcomes (CCFO): |
UNIT STANDARD CCFO IDENTIFYING |
Identify and solve problems
Assessment Criteria: Survey errors are identified and eliminated in accordance with surveying principles |
UNIT STANDARD CCFO WORKING |
Work effectively with others
Assessment Criteria: Setting out principles are explained |
UNIT STANDARD CCFO ORGANISING |
Employ self management |
UNIT STANDARD CCFO COLLECTING |
Manage information
Specific Outcome: Understand and apply surveying techniques and principles Assessment Criteria: Information regarding dimensions and positions for surveying is extracted from drawings |
UNIT STANDARD CCFO COMMUNICATING |
Communicate effectively
Assessment Criteria: Setting out principles are explained |
UNIT STANDARD CCFO SCIENCE |
Demonstrate scientific and technological competence
Specific Outcome: Apply tachometric principles and set out work Assessment Criteria: |
UNIT STANDARD CCFO DEMONSTRATING |
Understand Contextual world-systems
Specific Outcome: Understand and apply surveying techniques and principles Assessment Criteria: All surveying and setting out activities are checked to comply with survey information and drawings |
UNIT STANDARD ASSESSOR CRITERIA |
N/A |
REREGISTRATION HISTORY |
As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. |
UNIT STANDARD NOTES |
N/A |
QUALIFICATIONS UTILISING THIS UNIT STANDARD: |
ID | QUALIFICATION TITLE | PRE-2009 NQF LEVEL | NQF LEVEL | STATUS | END DATE | PRIMARY OR DELEGATED QA FUNCTIONARY | |
Core | 23675 | National Certificate: Management of Building Construction Processes | Level 5 | Level TBA: Pre-2009 was L5 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
Core | 23683 | National Diploma: Management of Civil Engineering Construction Processes | Level 5 | NQF Level 05 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
Core | 48700 | Bachelor of Construction Management: Built Environment | Level 6 | Level TBA: Pre-2009 was L6 | Passed the End Date - Status was "Reregistered" |
2012-06-30 | CHE |
Elective | 20486 | National Certificate: Surveying | Level 4 | Level TBA: Pre-2009 was L4 | Passed the End Date - Status was "Reregistered" |
2023-06-30 | CETA |
PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: |
This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here. |
1. | Academic Institute of Excellence |
2. | Academy for Construction Skills (Pty) Ltd (ACS) |
3. | Construction Resource Development College |
4. | MTL Training and Projects |
5. | Raubex Construction Pty (Ltd) |
6. | South African Value Education (Pty) Ltd |
7. | Tjeka Training Matters Pty Ltd |
All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source. |