SAQA All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source.
SOUTH AFRICAN QUALIFICATIONS AUTHORITY 
REGISTERED UNIT STANDARD THAT HAS PASSED THE END DATE: 

Inspect, assemble, remove, replace/install and adjust section insulator runners on 3-kV DC overhead track equipment under "live" conditions 
SAQA US ID UNIT STANDARD TITLE
119891  Inspect, assemble, remove, replace/install and adjust section insulator runners on 3-kV DC overhead track equipment under "live" conditions 
ORIGINATOR
SGB Electrical Engineering & Construction 
PRIMARY OR DELEGATED QUALITY ASSURANCE FUNCTIONARY
-  
FIELD SUBFIELD
Field 12 - Physical Planning and Construction Civil Engineering Construction 
ABET BAND UNIT STANDARD TYPE PRE-2009 NQF LEVEL NQF LEVEL CREDITS
Undefined  Regular  Level 4  NQF Level 04  14 
REGISTRATION STATUS REGISTRATION START DATE REGISTRATION END DATE SAQA DECISION NUMBER
Passed the End Date -
Status was "Reregistered" 
2018-07-01  2023-06-30  SAQA 06120/18 
LAST DATE FOR ENROLMENT LAST DATE FOR ACHIEVEMENT
2024-06-30   2027-06-30  

In all of the tables in this document, both the pre-2009 NQF Level and the NQF Level is shown. In the text (purpose statements, qualification rules, etc), any references to NQF Levels are to the pre-2009 levels unless specifically stated otherwise.  

This unit standard does not replace any other unit standard and is not replaced by any other unit standard. 

PURPOSE OF THE UNIT STANDARD 
The learner credited with this unit standard will be able to:
  • Inspect;
  • Assemble;
  • Remove;
  • Replace/install;
  • Adjust section insulator runners on 3-kV DC OHTE under "live conditions correctly and safely whilst working independently thus contributing to the safe running of electric trains as well as ensuring the continuity of power supply in the rail sector. 

  • LEARNING ASSUMED TO BE IN PLACE AND RECOGNITION OF PRIOR LEARNING 
    It is assumed that learners are competent in the following:
  • Train Working Rules.
  • Mathematical Literacy at NQF Level 3.
  • Communication at NQF Level 3. 

  • UNIT STANDARD RANGE 
  • Equipment may include but is not limited to:

    > Personal protective equipment.
    > Train protection equipment.
    > Fire-Fighting equipment.
    > First-Aid equipment.
    > Equipment related to the inspection, assembling, removal, replacement/installation and adjustment of section insulator runners on OHTE related to isolated and earthed or live conditions.
  • Statutory requirements may include but are not limited to:

    > Relevant sections of Act. 85.
    > Code of Practice No 29.
    > Train Working Rules. (TWR).
    > Company-specific electrical safety instructions.
    > Relevant sections of the Explosives Act.
  • Work procedures may include but are not limited to company's:

    > Safety procedures related to isolated and earthed or live conditions.
    > Safe working methods related to isolated and earthed or live conditions.
    > Policies related to isolated and earthed or live conditions.
    > Installation procedures related to isolated and earthed or live conditions.
    > Maintenance procedures related to isolated and earthed or live conditions.
  • Manufacturers' specifications may include but are not limited to:

    > Dimensions of components.
    > Type of material from which components are manufactured.
  • This unit standard includes the assembling and installation of a section insulator on OHTE under "live" and/or isolated and earthed conditions while working independently.
  • Work permit conditions apply when work is performed under isolated and earthed conditions. 

  • Specific Outcomes and Assessment Criteria: 

    SPECIFIC OUTCOME 1 
    Communicate with relevant role players and complete relevant documentation. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    Job card is interpreted so that specified work can be executed correctly. 

    ASSESSMENT CRITERION 2 
    Relevant documentation is completed correctly. 

    ASSESSMENT CRITERION 3 
    Transport is arranged for personnel. 

    ASSESSMENT CRITERION 4 
    Communication relating to the removal, replacement/installation of adjustment section insulator runners on 3-kV DC OHTE is carried out with all role players. 

    SPECIFIC OUTCOME 2 
    Prepare to inspect, assemble, remove and replace section insulator runners. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    Tools, equipment and are obtained and verified for correctness. 

    ASSESSMENT CRITERION 2 
    Safe loading and off-loading of tools, material and equipment are ensured for correctness. 

    ASSESSMENT CRITERION 3 
    The necessary safety precautions at the worksite are taken to prevent injury to personnel. 

    ASSESSMENT CRITERION 4 
    Work permit is obtained correctly and timeously when work is performed under isolated and earthed conditions according to work-permit procedures. 

    ASSESSMENT CRITERION 5 
    Protection is placed correctly according to TWR. 

    SPECIFIC OUTCOME 3 
    Inspect, assemble, remove and replace section insulator runners. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    Company-specific safe work procedures are followed correctly. 

    ASSESSMENT CRITERION 2 
    Tools and equipment are placed and used safely and correctly. 

    ASSESSMENT CRITERION 3 
    Lifting equipment is used correctly and safely according to statutory requirements. 

    ASSESSMENT CRITERION 4 
    Section insulator runners are inspected for defects according to company and manufacturer's specifications. 

    ASSESSMENT CRITERION 5 
    Section insulator runners are assembled according to manufacturer's specifications. 

    ASSESSMENT CRITERION 6 
    Section insulator runners are removed and replaced in accordance with section insulator runners removal and replacement procedures. 

    ASSESSMENT CRITERION 7 
    Section insulator runners are adjusted in accordance with section insulator runner adjustment procedures and manufacturer's specifications. 

    SPECIFIC OUTCOME 4 
    Finalise the assembling, removal, replacement, installation and adjustment of section insulator and/or runners. 

    ASSESSMENT CRITERIA
     

    ASSESSMENT CRITERION 1 
    Quality checks are performed safely and correctly on section insulator and/or runners as per company-specific instructions and manufacturer's specifications. 

    ASSESSMENT CRITERION 2 
    Tools, equipment and material are removed safely and correctly. 

    ASSESSMENT CRITERION 3 
    Worksite is cleared according to company-specific instructions. 

    ASSESSMENT CRITERION 4 
    Protection is removed correctly in accordance with TWR. 

    ASSESSMENT CRITERION 5 
    Work permit is cancelled correctly and timeously according to work permit procedures when permit was issued. 


    UNIT STANDARD ACCREDITATION AND MODERATION OPTIONS 
  • Anyone assessing or moderating a learner against this unit standard must be trained, qualified, certified and re-certified as an assessor/moderator in the OHTE/Substation division in accordance with the specific validation regulations relevant to the specific unit standard and registered with the relevant ETQA.
  • Any institution offering learning that will enable the achievement of this Qualification must be accredited as a provider with the relevant ETQA or an ETQA that has a Memorandum of Understanding with a relevant ETQA.
  • The relevant ETQA or an ETQA that has a Memorandum of Understanding with the relevant ETQA will oversee assessment and moderation of assessment policies and guidelines for assessment and moderation.
  • Moderation must include both internal and external moderation of assessment. Moderation should also encompass achievement of the competence described both in individual Unit Standards as well as the integrated competence described in the Qualification. 

  • UNIT STANDARD ESSENTIAL EMBEDDED KNOWLEDGE 
    Learners can understand and explain:
  • The inspection, removal, replacement/installation and adjustment of section insulator runners on OHTE under isolated and earthed or live conditions.
  • The reading of section insulator or phase break manufacturer's layout plan.
  • The reading of electrification layout plan and diagrams.
  • Company specific electrical safety instructions.
  • Company specific safe working method.
  • The identification, purpose and function of parts and components of the OHTE.
  • The function, purpose and safe use of tools (hand and power).
  • Material identification and specifications related to section insulator and/or runners. 

  • UNIT STANDARD DEVELOPMENTAL OUTCOME 
    Learner and societal development:

    Learners can understand the importance of:
  • Safety in the workplace, as well as in the whole environment.
  • Being a team player in the work environment and in society.
  • Communicating effectively in the work environment and in society.
  • Their responsibility for the safety and well being of fellow workers and society at large. 

  • UNIT STANDARD LINKAGES 
    N/A 


    Critical Cross-field Outcomes (CCFO): 

    UNIT STANDARD CCFO IDENTIFYING 
    Problem solving:

    Learners can solve problems with regard to:
  • The correctness, quantity and quality of material, parts and components.
  • The suitability and functionality of material, equipment and tools.
  • Operational changes impacting on the removal, replacement, installation of section insulator and/or runners on OHTE.
  • The inspection, removal, replacement, adjustment of section insulator runners on 3-kV DC OHTE.
  • Availability and competence of assisting personnel. 

  • UNIT STANDARD CCFO WORKING 
    Teamwork:

    Learners can work effectively in teams when:
  • Applying safe work procedures.
  • Performing the inspection, removal, replacement, installation and adjustment of section insulator and/or runners on OHTE.
  • Restoring the worksite.
  • Loading and off-loading of tools, material and equipment. 

  • UNIT STANDARD CCFO ORGANISING 
    Self-organisation and self-management:

    A learner can organise and manage himself by:
  • Executing the task responsibly.
  • Maintaining a high level of discipline.
  • Adhering to time frames.
  • Adhering to safety and company specific policies and procedures. 

  • UNIT STANDARD CCFO COLLECTING 
    Information evaluation:

    Learners can interpret and evaluate the contents of:
  • A job order.
  • Section insulator and/or runner manufacturer's layout plan with associated symbols.
  • Section insulator and/or runner specifications, removal, replacement, installation and adjustment procedures. 

  • UNIT STANDARD CCFO COMMUNICATING 
    Learners can communicate effectively with relevant role-players when:
  • Organising material, tools, equipment and personnel.
  • Completing relevant documentation.
  • Placing and removing protection.
  • Obtaining and cancelling work permit. 

  • UNIT STANDARD CCFO SCIENCE 
    Learners can use science and technology by using:
  • Hand tools and equipment.
  • Communication media. 

  • UNIT STANDARD CCFO DEMONSTRATING 
    Inter-relatedness of systems:

    Learners can understand the role of overhead track equipment in the rail sector. 

    UNIT STANDARD ASSESSOR CRITERIA 
    N/A 

    REREGISTRATION HISTORY 
    As per the SAQA Board decision/s at that time, this unit standard was Reregistered in 2012; 2015. 

    UNIT STANDARD NOTES 
    Values:
  • Safety consciousness.
  • Accuracy.
  • Neatness.
  • Pro-activeness.
  • Quality consciousness.
  • Time consciousness.

    Supplementary information:

    Terminology:
  • OHTE refers to overhead track equipment.
  • Act 85 refers to safety, health and environmental regulations.
  • TWR refers to train working rules.
  • A section insulator refers to a device for dividing a contact wire and catenary wire into electrical sections, while maintaining mechanical continuity and continuous path for pantographs.
  • A runner refers to a component of a section insulator.
  • Job order refers to:
    > Job card.
    > Job instruction.
  • Communication media can include but are not limited to:
    > 2-way radios.
    > Cellular phones.
    > Trunk radios.
    > Hand-held emergency telephones.
  • Logbook refers to evidence of training and job performance.
  • Worksite refers to the location where the task is to be performed. 

  • QUALIFICATIONS UTILISING THIS UNIT STANDARD: 
      ID QUALIFICATION TITLE PRE-2009 NQF LEVEL NQF LEVEL STATUS END DATE PRIMARY OR DELEGATED QA FUNCTIONARY
    Core  49774   Further Education and Training Certificate: Construction and Maintenance of Overhead Track Equipment  Level 4  NQF Level 04  Passed the End Date -
    Status was "Reregistered" 
    2023-06-30  TETA 


    PROVIDERS CURRENTLY ACCREDITED TO OFFER THIS UNIT STANDARD: 
    This information shows the current accreditations (i.e. those not past their accreditation end dates), and is the most complete record available to SAQA as of today. Some Primary or Delegated Quality Assurance Functionaries have a lag in their recording systems for provider accreditation, in turn leading to a lag in notifying SAQA of all the providers that they have accredited to offer qualifications and unit standards, as well as any extensions to accreditation end dates. The relevant Primary or Delegated Quality Assurance Functionary should be notified if a record appears to be missing from here.
     
    1. Palesa Rail Academy 



    All qualifications and part qualifications registered on the National Qualifications Framework are public property. Thus the only payment that can be made for them is for service and reproduction. It is illegal to sell this material for profit. If the material is reproduced or quoted, the South African Qualifications Authority (SAQA) should be acknowledged as the source.